Sunbury's multi-deck car park. Photo / Sunbury Life.

Sunbury’s multi-deck car park ready to open

Sunbury’s new multideck car park, fast-tracked and completed ahead of schedule, will open to commuters on Monday 22 July.

The car park, on the busy corner of Station St and Evans St, adds 311 free commuter parking spaces. It will also provide storage for bicycles and improved access to the station for pedestrians.

The building has accessible parking spaces, lifts, improvements for cyclists and pedestrians, and features eight charging bays for electric vehicles.

The car park was due to be completed in December, and while the original cost was put at $25m, the figure was revised in December 2023 to $36m. The final figure is put at $39.1m.

An email sent by Ruth Robles McColl, Hume City Council’s Manager Strategic Projects and Places, confirmed the opening date and states the Victorian Government, Commonwealth Government, and Hume City Council partnered to deliver the car park.

Sunbury’s multi-deck car park offers 311 free car spaces, EV charging stations, and room for bicycles. Photo / Sunbury Life.

What has happened so far 

  • September 2020 – Project is announced
  • July 2021 – Council undertook a statutory planning process to get approval to build the  car cark 
  • July 2021 – July 2022 – Council worked with State Government and landowners to resolve complex site issues
  • September 2021 – Council completed a design and feasibility study and publicly released concept images.   
  • July 2022 – Council undertook an RFP process to find a developer to build the  car park
  • September 2022 – State Government and Council unveiled car park site to announce construction dates
  • December 2022 – Council awarded contract
  • January – June 2023 – Site preparation and finalisation of documentation
  • June 2023 – Construction commenced 